Home
Platform
Services
Industries
Resources
Company
Schedule a Demo
Guide · Fundamentals · 6 min read

What is a turnaround, shutdown or outage?

Founder, EZTRAK

A turnaround is a planned, periodic shutdown of a process unit or plant to do the maintenance, inspection and capital work that cannot be done while it runs. Refineries call it a turnaround, chemical plants a shutdown, power stations an outage. All three run through the same seven phases, cost tens of millions of dollars in weeks, and are won or lost in planning.

What is a turnaround, shutdown or outage?

01The definition

A turnaround (also written TAR, or STO for shutdown, turnaround and outage) is a scheduled event in which a process unit, or a whole plant, is taken out of service so that work requiring it to be down can be done: internal inspections, catalyst changes, exchanger bundle replacements, vessel repairs, valve overhauls, and capital projects tied in while the unit is open. It is planned a year or more ahead, executed in two to eight weeks by several hundred to several thousand contractors, and repeated on a cycle of roughly three to six years per unit.

02Same event, three names

Industry Name What is distinctive
Refining Turnaround Several units on one site, each on its own cycle; the largest events in scope and spend
Chemical and petrochemical Shutdown Multi-unit sites with shared utilities, batch and continuous processes side by side, specialty materials
Power generation Outage A fixed return-to-service date tied to demand; every hour down is lost revenue
LNG Turnaround Liquefaction trains with cryogenic long-lead material, remote sites, and a return date that is a contractual commitment

The vocabulary differs; the work does not. Each one is scope, work packages, material, contractors and cost, compressed into a fixed window. The industry pages cover what each sector adds.

03Why they cost so much

Two costs run at once. The first is the spend: contractor labor, material, equipment rental and specialist services, often $20 million to $200 million on a large unit. Material alone is 30 to 40% of that. The second is lost production: a unit that is down earns nothing, so every shift of overrun has a price measured in product. On a power outage the second cost is explicit; on a refinery it is the margin on every barrel not made.

The two costs pull against each other. Spending more to finish earlier can pay for itself; finishing late because material was not staged never does.

04The seven phases

  1. Front-end loading. Define the business case, the window and the budget. Identify long-lead material, often 40 weeks or more out.

  2. Scope development and freeze. Build the scope list from inspection history, reliability data and capital projects. Freeze it, with a change process for anything added later.

  3. Planning. Develop a work package per scope item: steps, crew, duration, permits, isolations, drawings. Estimate hours and cost. Sequence the packages into a schedule.

  4. Material. Requisition, purchase, receive and stage material against each package and its activity date.

  5. Contracting. Issue scope to contractors, compare bids, award, and build the manpower plan by day.

  6. Execution. Shut down, open the equipment, do the work, capture progress, QA and discovery work by shift, and close each package within hours of completion.

  7. Closeout and lessons. Reconcile cost, close purchase orders, record what changed, and carry the packages and lessons into the next cycle.

05Who is involved

A turnaround manager owns the event. Planners build the packages. A scheduler owns the critical path. A material coordinator owns requisition to staging. A cost engineer owns the budget and forecast. Operations owns the shutdown and start-up. Inspection and QA own the findings. Contractors, often the majority of people on site, execute the work. On a large event the planning team alone can be 20 to 40 people for a year.

06What turnaround planning involves

Planning is phases 2 through 5: turning a scope list into packages that a crew can execute, with the material staged, the contractor awarded and the cost known before the unit comes down. The measure of good planning is readiness at the gate: what share of packages are complete, what share of material is staged, and how much scope was added after the freeze. The measure of poor planning is discovered in execution, as idle crews, emergency orders and a schedule nobody trusts.

07Where turnarounds go wrong

Failure When it shows
Scope added after the freeze without approval On the invoice
Material tracked only to the warehouse dock The morning the crew needs it
Work packages kept in contractors' own tools At demobilization, when the knowledge leaves
Progress collected by phone and radio In the close-out backlog at the end of the event
Cost assembled monthly from contractor reports Three weeks after the decision it should have informed
Each event planned from scratch Every cycle

08A turnaround by the numbers

Measure Typical range
Planning lead time 12 to 18 months
Long-lead material ordered 40 weeks or more ahead
Execution window 2 to 8 weeks
People on site at peak 500 to 3,000
Work packages on a large unit 300 to 1,500
Material share of spend 30 to 40%
Scope added after the freeze 5 to 15% of hours
Cycle between turnarounds on one unit 3 to 6 years

09Terms used on every turnaround

Term Meaning
Scope freeze The date after which additions need formal approval
Work package The planned job for one scope item: steps, crew, duration, permits, drawings, material
Front-end loading (FEL) The planning done before the event is approved and funded, checked at gates
Long-lead material Items whose lead time sets the planning calendar
Discovery work Scope found when equipment is opened, added after the freeze
Laydown yard The area where material is received and held before staging
Staging Setting material aside for a specific package before it is needed
Close-out Closing a package after the work is complete, with QA accepted
PMI Positive material identification: confirming the alloy of an installed item
Readiness The share of packages that can be executed as planned on the day they are needed

10Where software fits

A scheduler holds the activities and the critical path, and an ERP holds purchasing and finance. Neither holds the work itself. Turnaround software sits between them: the scope and work packages, the material from requisition to installation, the contractor estimates and daily cost, and the field capture that keeps all of it current by shift. The EZTRAK platform does that with three modules: Pilot for planning and execution, Flow for material and Vault for cost, working alongside SAP and Primavera P6.

11How to tell a well-run turnaround from a poorly run one

Ask four questions after the event. Did it finish on the date, measured in shifts? Did it finish on budget, including the scope added after the freeze? How many jobs were still open 24 hours after the work was done? And could the next turnaround on the same unit start from this one's packages, material lists and contractor performance, or will it start from a blank sheet? A site that can answer all four from a system, rather than from memory, has the planning under control. A site that can answer none of them is paying for the same lessons every cycle. The gap between the two is rarely effort; it is where the information lived while the event was running.

13Frequently asked questions

How long does a turnaround last?

Execution usually runs two to eight weeks. Planning starts 12 to 18 months earlier, and long-lead material is ordered 40 weeks or more ahead.

How often does a unit have a turnaround?

Every three to six years, set by inspection intervals, catalyst life and regulatory requirements.

What is the difference between a turnaround and routine maintenance?

Routine maintenance happens while the unit runs. A turnaround is the work that needs the unit down, done all at once to limit lost production.

What is STO?

Shutdown, turnaround and outage: the collective term for the same kind of event across industries.

See the seven phases on one platform.

Fifteen minutes on a live system: scope, packages, material, contractors and cost in one place. Or call 626-327-6348.

Book a demonstration